Agency Services

  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
 

 

 

180200 kg handeled in Esbjerg - Multi modal transport
 

On behalf of client Niels Winther & Co. handeled the heavy lift of a transformer of 180 tons.

The lift was carried out by two cranes doing twin lift and discharged from coaster onto haulier.

As safety is always first we had a "tool box meeting" with crane operators, dockers and vessel crew before commencing lift and after that lift took 45 minutes from on-hooking to off-hooking.

The transformer was then transported by road to receiver.

Niels Winther & Co. has many years of experience with door-to-door solutions and are specialised within heavy lift.

On this particular shipment sea freight was handeled by third party.

 

 